Pacific Fleet Sub Drive-In MSF, Project P-587
Beckoning Point, Pearl Harbor, Hawaii
- A new 213-meter (700-foot) non-magnetic concrete slip, installation of x-, y-, and z-loop cables, electrical Rectifier Building, and other improvements.
- Over water soil borings to depth of over 150 feet below water table.
- Assisted in update of 1391 and during preparation of design and Design-Build Request for Proposal documents.
- Currently providing consultation during construction.
- Geotechnical feedback helped in siting of finger piers to more favorable subsurface conditions.